Dubai Metro Blue Line 29% Complete: New Trains Unveiled, Opening on 9 September 2029

22 November 2026

The Dubai Metro Blue Line, an AED 20.5 billion project, is 29% complete and remains on schedule to open on 9 September 2029. On 22 November 2026 Sheikh Hamdan bin Mohammed bin Rashid Al Maktoum, Crown Prince of Dubai, inspected the worksite at Dubai Festival City, where the Roads and Transport Authority (RTA) unveiled the design of the new Blue Line trains. More than 14,000 workers have put in over 33 million working hours on the 30 km line, which will have 14 stations and serve Mirdif, International City, Dubai Silicon Oasis, Dubai Creek Harbour and other fast-growing districts.

Where construction stands in November 2026

Sheikh Hamdan was received by Mattar Al Tayer, Director-General and Chairman of the Board of Executive Directors of the RTA, together with officials from the RTA and the MAPA, LIMAK and CRRC consortium that is delivering the project. According to the figures released by WAM, overall completion has reached 29%. Progress by component:

  • underground stations: 32%;
  • tunnel excavation: 55%;
  • elevated stations: 16%;
  • bridge works: 17%;
  • bridge piers: 62%.

For comparison, in May 2026, when Sheikh Mohammed bin Rashid Al Maktoum launched the main tunnelling works, the project stood at 20% completion with more than 10,000 workers on site. In six months the workforce has grown to more than 14,000 and overall progress has moved up by nine percentage points.

The opening date of 9 September 2029 marks the 20th anniversary of the launch of the Dubai Metro in 2009. Sheikh Hamdan confirmed it in a post on X, saying that work is gathering pace ahead of the scheduled opening.

The new Blue Line trains

The new train model has a design capacity of 675 passengers per journey and a total capacity of 1,246 passengers per journey. The interior has three main categories: Gold Class, Silver Class and a dedicated carriage for women and children.

Gold Class includes contemporary seating, wireless chargers for smart devices, digital screens showing advertisements, the time and date, and intelligent lighting that adapts automatically to ambient conditions. The ceiling design evokes a star-studded sky. Silver Class and the carriage for women and children are designed to balance capacity, comfort and ease of movement, with large windows and digital screens that show the route and stations.

The trains also carry smart systems: advanced cameras that detect obstacles on the track, intelligent cameras that count passengers and monitor occupancy, and real-time image and data processing. The RTA says these systems will help track passenger density and improve capacity and operational efficiency.

A train systems laboratory with CASCO Signal

As part of the Blue Line project, the RTA is establishing a research and development centre and innovation laboratory with CASCO SIGNAL LTD., a company that specialises in signalling, communications and control systems for metro and railway networks. The centre includes a train systems simulator, described as the first laboratory for developing train systems in the Middle East. The simulator will be used to test the integration of signalling, communications and control systems and to simulate operating conditions before they enter service.

According to the RTA, the laboratory will allow acceptance testing and technical verification to be carried out locally in Dubai, cut testing time by 85% and raise the accuracy of the train punctuality indicator to more than 99.7%.

Sheikh Hamdan also viewed the Automated Rail Infrastructure Inspection System (ARIIS), developed by the RTA Rail Agency. The mobile system uses LiDAR technology and artificial intelligence to detect defects in rail infrastructure. Its targets include an 80% reduction in inspection time, a 50% reduction in resources used and ten times more data collected and analysed.

Route, stations and the Creek bridge

The Blue Line runs for 30 km, of which 15.5 km are underground and 14.5 km above ground. Its 14 stations include three interchange stations: two connect the line to the Red and Green Lines, at Centrepoint and Creek stations, and one links the two branches of the Blue Line. The line will serve Mirdif, Al Warqa, International City, Dubai Silicon Oasis, Dubai Academic City, Dubai Festival City and Dubai Creek Harbour. According to WAM, the communities along the route are expected to be home to around one million people by 2040.

The stations follow five architectural concepts. The Emaar Properties Station at Dubai Creek Harbour is inspired by the concept of a crossing gateway. At 74 metres, it will be the tallest metro station in the world. It covers about 11,000 square metres and has an estimated capacity of around 160,000 riders per day. The other four concepts are inspired by water, air, fire and earth.

The line will cross Dubai Creek on a 1.3 km bridge, the first Metro crossing over the Creek. It is built from precast concrete segments installed with specialised cranes and platforms that work from completed piers, which reduces the need for floating cranes and keeps marine traffic moving during construction.

The visit also covered the nol payment system. This month the RTA is launching the next generation of nol-Jaywan cards with Al Etihad Payments, a subsidiary of the Central Bank of the UAE.

What this means for companies in Dubai

The Blue Line does not change anything for companies today: the opening is almost three years away. Its value for business is in planning. The line will connect districts where many companies keep offices, warehouses and staff housing, such as International City, Dubai Silicon Oasis, Dubai Festival City and Mirdif, with the existing Red and Green Lines. When a company signs a multi-year lease, the expected 2029 metro access is one of the factors to weigh alongside rent, licence type and the location of clients and staff.

The Blue Line is part of a wider expansion of the network that we covered in our article on the Blue and Gold Line plans and in the news on the Metro extension to Al Maktoum Airport. The choice of where to register a company and rent an office starts with the jurisdiction, mainland or free zone, which we explain in our guide to company formation in the UAE.

Checklist for a company choosing an office or warehouse in the eastern districts of Dubai:

  • plan with current transport options, since the Blue Line opens on 9 September 2029;
  • map where your clients and staff are, and which future Blue Line stations are close to them;
  • compare mainland and free zone options for the licence and the office address;
  • check that the lease term and the registered address match your licence and visa plans;
  • plan the corporate bank account and staff visas early, as they depend on the licence.

How Atlant Capital can help

Atlant Capital helps entrepreneurs and investors set up and run a business in Dubai and across the UAE. We compare jurisdictions, select the business activities that fit your model and handle company setup in the UAE from the first application to the incorporation documents. We also prepare the documents for corporate bank account opening, which a new company needs to start working with clients.

Conclusion

The Dubai Metro Blue Line is 29% complete, with more than 14,000 workers and over 33 million working hours on site. The new trains will carry up to 1,246 passengers per journey and offer Gold Class with wireless chargers, while the RTA is setting up the first train systems laboratory in the Middle East with CASCO Signal. The AED 20.5 billion line, 30 km long with 14 stations and the 74 metre Emaar Properties Station, is scheduled to open on 9 September 2029.

Source: WAM, The National.

FAQ

How complete is the Dubai Metro Blue Line?

As of 22 November 2026, the Dubai Metro Blue Line is 29% complete. Tunnel excavation is at 55%, underground stations at 32%, elevated stations at 16% and bridge works at 17%, with more than 14,000 workers and over 33 million working hours on the project.

When will the Dubai Metro Blue Line open?

The Blue Line is scheduled to open on 9 September 2029, the 20th anniversary of the launch of the Dubai Metro. Sheikh Hamdan bin Mohammed confirmed the date after inspecting the worksite on 22 November 2026.

How many passengers will the new Blue Line trains carry?

The new Blue Line trains have a design capacity of 675 passengers per journey and a total capacity of 1,246 passengers per journey. They have Gold Class, Silver Class and a carriage for women and children, and Gold Class includes wireless chargers for smart devices.

Which areas will the Dubai Metro Blue Line serve?

The 30 km line with 14 stations will serve Mirdif, Al Warqa, International City, Dubai Silicon Oasis, Dubai Academic City, Dubai Festival City and Dubai Creek Harbour. It connects to the Red Line at Centrepoint and to the Green Line at Creek station.

Need the same handled for your company?

We register companies, open corporate bank accounts and arrange residency in the UAE. Describe your case and we will tell you what it takes.

Book a consultation

Нужно то же самое для вашей компании?

Регистрируем компании, открываем корпоративные счета и оформляем резидентство в ОАЭ. Опишите задачу, и мы скажем, что для этого нужно.

Записаться на консультацию

From the same categoryИз той же рубрики