Dubai Awards AED 56.5 Billion in New Al Maktoum Airport Contracts

26 November 2026

Dubai has awarded a new series of contracts worth about AED 56.5 billion for Al Maktoum International Airport, Crown Prince Sheikh Hamdan bin Mohammed announced on Thursday, 26 November 2026. Together with about AED 23.815 billion awarded in the previous phase, the total value of contracts and packages awarded for the project now stands at about AED 80 billion. The new packages cover the West Terminal, Concourses 1 to 4 and the main power substations, and about 14,000 people are already working on site. The airport remains on course to start operations in 2032, and after its final phase it is designed to handle more than 260 million passengers a year, which the Dubai Government says will make it the largest aviation hub in the world.

What was announced on 26 November

Sheikh Hamdan, who is also Deputy Prime Minister and Minister of Defence of the UAE and Chairman of The Executive Council of Dubai, said the contracts were awarded under the directives of Sheikh Mohammed bin Rashid Al Maktoum, Vice President and Prime Minister of the UAE and Ruler of Dubai. Sheikh Ahmed bin Saeed Al Maktoum, Chairman of the Dubai Aviation City Corporation and of Dubai Aviation Engineering Projects (DAEP), said the project has entered a phase of large-scale construction and that the contracts and delivery sequence are structured so that several sites progress in parallel. The key figures from the official announcement:

  • New awards: about AED 56.5 billion.
  • Earlier awards by DAEP: about AED 23.815 billion, covering enabling works, substructure packages and the contracts for the Automated People Mover (APM) and the Baggage Handling System (BHS).
  • Total awarded to date: about AED 80 billion.
  • Workforce across the active packages: about 14,000 people, with more than 21.3 million cumulative working hours.
  • Contractors: not named in the announcement.

What the AED 56.5 billion covers

According to the Dubai Media Office, the new awards fall into four groups of works that will run at the same time during Phase One.

West Terminal Building and Concourse 1

Substructure and associated infrastructure: basements, underground tunnels, access ramps, short-term car parks and the Ground Transportation Centre, together with metro interface works and landside bridges. The packages also include underground corridors for ground service equipment (GSE), the principal BHS backbone network and utility networks for electricity, water, telecoms, sewerage and stormwater drainage.

Concourses 2 and 3

Superstructure works above ground: the main concourse buildings, rotundas, structural steel bridges and the supports for passenger boarding bridges. The scope also covers large-span steel roof spaceframes, facades, roofing, architectural fit-out, mechanical, electrical and plumbing (MEP) installations and special airport systems inside the two concourses.

Concourse 4

Substructure and underground infrastructure: basements, tunnels, access ramps, GSE corridors, utility networks and part of the BHS backbone, which prepares the ground for the later stages of this concourse.

Power infrastructure

Two principal 132/11 kV substations with power cabling and related electrical infrastructure. The package covers construction, installation, testing, commissioning and handover.

How far construction has progressed

In June 2026 the Dubai Government said that contracts worth AED 13 billion were under execution and that packages worth more than AED 55 billion would be awarded by the end of the year. The awards of 26 November exceed that figure. The latest progress data from DAEP:

  • excavation across the project has exceeded 24.23 million cubic metres, and backfilling has exceeded 5.2 million cubic metres;
  • 7,635 piles have been completed;
  • on the substructure packages for Concourses 2 and 3, more than 875,603 cubic metres of concrete have been placed and over 226,270 tonnes of reinforcement steel installed;
  • enabling works in the Concourse 2 and 3 zones and in the central area of the site are nearing completion, while work continues in the West Terminal, Concourse 1, Ground Transportation Centre and Concourse 4 zones.

In June DAEP also said that the on-site workforce, then about 9,000 people, was expected to rise to around 120,000 at peak construction. Today the figure stands at about 14,000.

What the finished airport will look like

After its final phase, Al Maktoum International Airport is planned to have:

  • annual capacity of more than 260 million passengers and 12 million tonnes of air cargo;
  • five parallel runways operating independently;
  • two passenger terminals and seven concourses connected to more than 430 aircraft stands;
  • an integrated Automated People Mover and connections between air, rail and road transport.

The Dubai Government links the project to the Dubai Economic Agenda D33, which aims to double the size of the emirate’s economy. Operations at the new airport remain scheduled to begin in 2032. Dubai has also approved an extension of the Metro to the airport, with services planned from 2031, as we covered in our report on Dubai Metro reaching Al Maktoum Airport City.

What it means for companies in the UAE

The announcement does not change any rule, fee or procedure for businesses, and the official release does not list the winning contractors. What it does set out is the scale and order of the work: superstructure and fit-out of two concourses, substructure for the terminal and two more concourses, and the power network, all running in parallel. In our view this is most relevant for three groups:

  • Construction, MEP, steel, facade and building-systems firms that want to work as subcontractors or suppliers to the main contractors. On large projects main contractors typically prequalify their subcontractors, and a UAE trade licence with the right activities is the starting point.
  • Service companies around the site: workforce housing, transport, catering, equipment rental and recruitment. The expected growth of the workforce from about 14,000 towards the peak level means more hiring and more work visas.
  • Aviation, logistics and cargo businesses that plan their Dubai footprint around the future move of operations from Dubai International to Al Maktoum International.

How Atlant Capital can help

If you plan to bid for subcontracts or supply work on Dubai infrastructure projects, the first step is a UAE company with the right licence activities. A short checklist before you approach a main contractor:

  • choose licence activities that match the work you want to do, for example construction contracting, MEP contracting or building materials trading;
  • decide between mainland and free zone based on where your clients and sites are;
  • prepare a company profile, references and certificates for contractor prequalification;
  • plan visas and accommodation for the staff you will bring before mobilisation.

Our company setup team handles mainland and free zone registration, and our work visa and residency service covers visas for your staff. For a step-by-step overview of licences, costs and timelines, read our UAE company formation guide. For the earlier stage of the project, see our report on the AED 55 billion contract pipeline for Al Maktoum airport.

Bottom line

On 26 November 2026 Dubai awarded about AED 56.5 billion in new contracts for Al Maktoum International Airport, bringing the total awarded to about AED 80 billion. The packages cover the West Terminal, Concourses 1 to 4 and two principal substations, with about 14,000 people on site. The airport remains on course to start operations in 2032 and is designed for more than 260 million passengers a year after its final phase.

Source: Dubai Media Office, Khaleej Times.

FAQ

How much has Dubai awarded for Al Maktoum International Airport so far?

About AED 80 billion. On 26 November 2026 Dubai announced new contracts worth about AED 56.5 billion, on top of about AED 23.815 billion awarded earlier by Dubai Aviation Engineering Projects for enabling works, substructures, the Automated People Mover and the Baggage Handling System.

What do the new Al Maktoum airport contracts cover?

They cover substructure and infrastructure for the West Terminal Building, Concourse 1 and Concourse 4; superstructure, roof spaceframes, facades, fit-out, MEP and airport systems for Concourses 2 and 3; and two principal 132/11 kV substations with power cabling.

When will Al Maktoum International Airport open?

The Dubai Government says the airport remains on course to start operations in 2032 under its master plan. After the final phase it is designed for more than 260 million passengers and 12 million tonnes of cargo a year, with five parallel runways and more than 430 aircraft stands.

Which companies won the Al Maktoum airport contracts?

The official announcement of 26 November 2026 did not name the contractors. Dubai Aviation Engineering Projects manages the programme, including the sequencing of packages, technical interfaces, quality, safety, cost and schedule.

Need the same handled for your company?

We register companies, open corporate bank accounts and arrange residency in the UAE. Describe your case and we will tell you what it takes.

Book a consultation

Нужно то же самое для вашей компании?

Регистрируем компании, открываем корпоративные счета и оформляем резидентство в ОАЭ. Опишите задачу, и мы скажем, что для этого нужно.

Записаться на консультацию

From the same categoryИз той же рубрики